Project Updates

Updated : August 9, 2016 

L36 Patching and Resurfacing
The Bridge Approaches are complete, other than joint sealing.  Midwest Contractors believes they will finish patching this week (8/13).  Western Engineering plans to finish milling on 8/11 and start the first lift of paving on Friday (8/12).  Paving depending upon weather will take 5-6 days to complete.  The shoulders and guardrail still need to be completed and will be scheduled soon.

G30 Silver Creek Bridge
The existing bridge has been removed and the substructure of the new bridge is being constructed.  Once the substructure is completed the work becomes less weather dependent, but also more labor intensive.

Desoto Avenue
Drainage Structures and paving has been completed West of the Tunnel.  The East portion and shoulder reconstruction on the West portion remain to be done.

Old Lincoln Highway Pigeon Creek Bridge
The project has been let, the contract is pending.

Coldwater Ave (L36)
340th Street (L66)
Old Lincoln Hwy Bridge, Over Simon Run
Desoto Ave, Boyer River Bridge
Mahogany Road (G30)
Detours for Projects

Thank you for your patience while we saved up the money to accomplish this work and for that given during the inconvenience of reconstruction.

In the Spotlight

Hope 4 Iowa

The HOPE 4 IOWA Crisis Call Line connects individuals in crisis to a helping hand and the resources to address and improve mental wellness. Available 24/7. For more information visit our website here.

 

 

 

 

 

 

 

  • 1
  • 2

Pottawattamie County Emergency Notification System

The Alert Iowa system serves all residents within Pottawattamie County and it's Communities.

The Pottawattamie County Emergency Management Agency has implemented The Alert Iowa system, a high-speed notification solution and Weather Warning service. This no-charge service is available to businesses.

Click Here To Register